​Impacts at Worksite #2 - East of 111 Street and south of 34 Avenue

At Worksite #2, we'll first construct a shaft to receive the tunnel boring machine (MTBM) from Worksite #1A and turn the MTBM to tunnel east along 34 Avenue.

During this work, you'll encounter:

  • No traffic impacts at this location.
  • A potential for tree removal to accommodate the shaft construction.
  • The multi-use trail adjacent to work area along 111 Street will remain open during construction.
  • Regular construction activities from Monday to Saturday, 7:00 a.m. to 9:00 p.m. 
  • Work taking place 24 hours a day during the tunneling period
  • The tunneling period is estimated to start 3 months after the start of the shaft construction
  • A portion of this work will include 24 hours a day, 7 days a week construction. The estimated timeline is fall 2021 to spring 2023 – 411 days
  • Heavy traffic along the haul route; tandem trucks and equipment will be coming down the haul route 5-7 times a day. Trucks will enter and exit the worksite using 111 Street or 34 Avenue.