​Zone A – 111 Street from Saddleback Road/29A Avenue to 34 Avenue 

Three worksite locations will support the construction process, with anticipated timelines as follows:

  • Worksite #1A - Westbound on 29A Avenue and on the east side of 111 Street – Spring 2023 to Spring 2024
  • Worksite #1B - 111 Street southbound, left turn lane onto 29A Avenue – Fall 2023 to Summer 2024
  • Worksite #2 - In the green space east of 111 Street and south of 34 Avenue – April 2023 to Spring 2024

​Anticipated Zone A Impacts

​Traffic​​​
Worksite 1A​
  • ​​One northbound lane on 111 Street, north of Saddleback Road/29A Avenue will be closed.
  • The right hand turning lane from westbound 29A Avenue onto northbound 111 Street will be closed. Vehicles will be able to turn right, onto the left northbound lane from the intersection.​
Worksite 1B
  • No parking will be permitted on the south side of 45 Avenue east of 106 Street.
​Sidewalks/walkways
​Worksite 1A
  • ​The sidewalk on the east side of 111 Street north of 29A Avenue will be closed. Pedestrians will be detoured to the west side of 111 Street.
​Other

​Worksite 1A
  • ​​Bus stop #4582 will be relocated on the east side of 111 Street to north of the work area.​

Worksite 2

  • ​A portion of the green space on the southeast corner of 111 Street and 34 Avenue will be utilized as a work area. The area will be fully fenced and secured.
​Working Hours
Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required,
these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to
5:00 p.m. During tunneling, the tunnel boring machine will be running 24/7 at Worksite #2.
​Haul Route
​Trucks and equipment will access all the worksites from 111 Street. Temporary lanes closures
may be in effect.

Please note, impacts may change based on City of Edmonton Traffic approvals. Advanced notification will be provided to residents and businesses in the local area before work begins.