During the first stage of this project, we'll be working at 6 different locations, as noted in the map below. In the summer of 2020, we started work at locations #1 and #2, followed by #3 in the fall.

Please note, all timelines are estimates and may change based on construction progress at the first 2 locations.

 

Location overview

​​148 Street and Summit Drive

Estimated timeline:
Week of July 13, 2020 to end of 2022

Impacts at this location

101 Avenue and Ravine Drive

Estimated timeline:
Week of September 14, 2020 to
spring 2022

Impacts at this location

148 Street and 99 Avenue

Estimated timeline:
Week of October 16, 2020 to
end of 2022

Impacts at this location

​101 Avenue, between 142 Street and 145 Street

Worksite #4 and #5 may be reduced to one worksite, which will decrease impacts from traffic and construction for residents.​​​

Estimated timeline:
Fall 2021 to Spring 2022

Impacts at this location

​​150 Street and 99 Avenue

Estimated timeline:
Early 2022 to end of 2022

Impacts at this location