​Project locations

During 2021, we'll be starting work at 4 different locations, as noted in the map below. In summer 2021, we will start work at locations #1A and #1B, followed by #2 in the fall.

Please note, all timelines are estimates and may change based on construction progress, construction conditions and weather.

Project map

 

​​Westbound on 29A Avenue and East of 111 Street

Estimated timeline:
June 14, 2021 to Summer 2022

Impacts at this location

​​111 Street Southbound left turn lane onto 29A Avenue

Estimated timeline:
June 14, 2021 to Spring 2022

Impacts at this location

East of 111 Street and South of 34 Avenue

Estimated timeline:
Fall 2021 to Summer 2023

Impacts at this location