​Zone B – 34 Avenue from 111 Street to 106 Street

Two worksite locations will support the construction process, with anticipated timelines as follows:

  • ​Worksite #3 - Eastbound on 34 Avenue, between 111 Street and 106 Street – March 2023 to Summer 2024
  • Worksite #4 - Northbound ​on 106 Street and north of 34 Avenue – April 2023 to Spring 2024

​Anticipated Zone B Impacts

​Traffic​​​
Worksite 3
  • ​Two eastbound lanes on 34 Avenue between 111 Street and 108 Street will be closed. The westbound lanes will be converted to one lane in each direction to allow two-way traffic.​

Worksite 4
  • ​One northbound lane on 106 Street from the intersection at 34 Avenue and heading north past the work area will be closed.
  • T​he westbound curb lane on 34 Avenue at 106 Street will be closed.
​Sidewalks/walkways
​Worksite 4
  • ​The shared-use path at the northeast corner of the intersection at 34 Avenue and 106 Street will be closed. Pedestrians will be detoured south of the worksite.
  • No crossing will be permitted across 106 Street on the north side of 34 Avenue. Pedestrians will be detoured to the south side of the intersection to cross.​
​Other

​Worksite 3
  • A portion of the greenspace along the south side of 34 Avenue between 111 Street and 108 Street will be utilized as a work area. The area will be fully fenced and secured.​
​Working Hours
Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required,
these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to
5:00 p.m. During tunneling, the tunnel boring machine will be running 24/7 at Worksite #3.
​Haul Route
​Trucks and equipment will access all the worksites from 34 Avenue. Temporary lane closures
may be in effect.