The Duggan sanitary sewer line services neighborhoods in southwest Edmonton, from Steinhauer up to Bonnie Doon. Construction on the new Duggan Tunnel began in March 2023 and is expected to be completed by Summer 2025.
The Duggan tunnel sanitary sewer moves wastewater from south Edmonton to the Gold Bar Wastewater Treatment Plant. The existing sewer is approximately 30 metres deep and was originally built by hand. The existing Duggan sanitary tunnel services the Edmonton region highlighted on the map:
EPCOR is aware of consistent sewer odour issues in several neighborhoods along the alignment of the Duggan Tunnel, particularly in Steinhauer. This project is part of EPCOR’s Corrosion and Odour Reduction Strategy (CORe). The strategy aims to understand and mitigate sewer odour issues and will result in significantly reduced sewer odour city-wide by 2031. With completion of the new tunnel, we expect the major cause of how odour is formed and pushed out into the communities to be notably diminished.
The existing Duggan tunnel serves as both a sanitary and storage tunnel and is just over three kilometers long. This means that sanitary flows are stored in the tunnel during wet weather events.
The existing Duggan tunnel has various shifts in depth along the alignment. When built in the 1960s, crews didn’t have the equipment or technology to easily tunnel through the existing sand layer, so they had to tunnel above it or below it. This variation in depth increases the movement of the sanitary flow (up and down), which increases the amount of odour generated. The new tunnel will flow by gravity (not up and down), which will reduce the amount of odour pushed out into the communities.
Sometimes, creating a change in one area can increase sewer odours in another. This is why EPCOR has a city-wide strategy and why the work must occur in a specific sequence.
Some steps have already begun, allowing for better access to infrastructure to inspect lines and investigate odour issues:
Residents are encouraged to report an issue any time an odour is overly strong by calling EPCOR Trouble at 780-412-4500. This helps us to track the odour to look for patterns and potential solutions.