Our site is customized by location. Please select the region of your service and we’ll remember your selection for next time.
Select a region for customized content and rates
Looks like you're in Canada
Looks like you're in the United States
Select a region for customized content and rates
Select a region for customized content and rates
Select a region for customized content and rates
ON THIS PAGE
The 99 Avenue sanitary sewer conveys wastewater from west Edmonton to the Gold Bar Wastewater Treatment Plant. The sewer is approximately 30 metres deep and services approximately 117,000 customers. Inspections have identified the existing trunk varies from fair to very poor condition and requires rehabilitation between 142 Street and 151 Street to ensure it continues to meet the current needs and growth for west Edmonton.
This project has been broken down into two stages:
The existing 99 Avenue sanitary trunk line that services over 100,000 customers needs to be replaced. This project will be completed in 2 stages, starting in July 2020 and we estimate the project will be finished by the end of 2024. In Stage 1, we are building a new tunnel along 99 Avenue, north on 148 Street and east on 101 Avenue. In Stage 2, we'll rehabilitate the existing tunnel on 99 Avenue. Once our work in done, both tunnels will be in service, increasing capacity in the trunk network.
About the 99 Avenue sanitary sewer
As seen by the map below, the 99 Avenue sanitary sewer moves wastewater from west Edmonton to the Gold Bar Wastewater Treatment Plant. The sewer is approximately 30 metres deep and services about 117,000 customers. For this project, the sewer needs rehabilitation between 142 Street and 151 Street.
This trunk line was built in 1975 and inspections have shown the existing trunk varies from fair to very poor condition. The existing trunk needs rehabilitation to ensure it continues to meet the current needs and growth for west Edmonton.
Current condition
Below is an example of the current tunnel in very poor condition in contrast to an image of what a tunnel should look like.
Stage 1
The first stage of this project is the construction of the new bypass tunnel started in July 2020 and is anticipated to be complete by the end 2022.
During this first stage of this project, we'll be working at 6 different locations. Find out more about each work location and the impacts to you.
Stage 2
The second stage of the project is the rehabilitation of the existing line and is scheduled to occur in 2022-2024. We're currently in the design phase for this part of the project.
Upon completion of the new construction (Stage 1) and the rehabilitation (Stage 2), both tunnels will be in service, which in turn will increase capacity of the trunk network.
This project will be completed in 2 stages; work started in July 2020 on Stage 1 and we estimate the entire project will be finished by the end of 2024.
Stage 1 timeline
The first stage of this project utilized 6 different work locations. Stage One work began in July 2020 and is now complete.
Stage 2 timeline
The second stage of the project is now underway and is anticipated to be completed in 2024.
Causes of possible schedule delays
While we always do our best to plan construction and abide by construction timelines communicated to the public, unexpected events can potentially occur which may delay the schedule. Some of these factors are:
Project locations
During the first stage of this project, we'll be working at 6 different locations, as noted in the map above. In the summer of 2020, we started work at locations #1 and #2, followed by #3 in the fall.
Please note, all timelines are estimates and may change based on construction progress at the first 2 locations.
Estimated timeline: Summer 2022 to end of Summer 2024
Traffic & pedestrian impacts
A full road closure will remain in effect on 99 Avenue between 150 Street and 151 Street, east of the alley way, during Stage Two construction.
The temporary sidewalk will be removed and the permanent sidewalks will be reopened to the public.
Haul route
The haul route for this location is as follows:
Estimated timeline: Fall 2023 to end of Summer 2024
Traffic impacts
A single lane along Summit Drive will be closed to use as a laydown area for the pipe segments used in the relining work. Parking restrictions adjacent to the site will be in effect during construction.
Residents may experience intermittent road closures as materials and equipment are brought to and from site.
Pedestrian impacts
The worksite for the construction of the working shaft will encompass a portion of the green space east of 142 Street and will be closed to the public for the duration of the Stage Two construction. EPCOR has worked with the City to temporarily relocate memorial benches located within the worksite.
Access to MacKinnon Ravine from the worksite location will be closed. Pedestrians and cyclists will be detoured west of 142 Street for access to the trail system.
To try to understand and reduce the construction impacts to the public, we've met with the Grovenor Community League, the Crestwood Community League, the West Jasper Place Community League, the Candy Cane Lane Committee, St. Andrew's Church and several other organizations that will be impacted by the work.
While we complete this work, you can expect to see activity that's typical to construction, including company/ contractor vehicles and equipment in your neighbourhood.
The Haul Route is the system of roads between a worksite and the nearest major intersection that construction vehicles will take when entering and exiting the worksite.
During this work, you'll see heavy traffic along the haul routes.
We'll also be working on different rehabilitation projects in the same area, during the same time. Find out how this work impacts the 99 Avenue project.
151 Street South Sanitary Trunk Rehabilitation Project
The 151 Street South Sanitary Trunk Rehabilitation Project is another project planned in the area to rehabilitate the existing trunk line. We have identified several sections of the trunk that need to be rehabilitated.
Inspections of the existing trunk line along 151 Street have been completed. Assessments are currently underway to determine the scope of work for the project.