​Project locations

During the first stage of this project, we'll be working at 6 different locations, as noted in the map below. In the summer of 2020, we started work at locations #1 and #2, followed by #3 in the fall.

Please note, all timelines are estimates and may change based on construction progress at the first 2 locations.

 

Location overview

Worksite #6

​​150 Street and 99 Avenue

Estimated timeline:
Summer 2022 to end of Summer 2024​​

IMPACTS AT THIS LOCATION

Worksite #8

​​142 Street and Summit Drive

Estimated timeline:
​Fall 2023 to end of Summer 2024​

IMPACTS AT THIS LOCATIO​N​​