Pumphouse #1 (groundwater treatment plant):
- The groundwater supply services approximately half of the town.
- Capacity: 8 ML/day
- Consists of well pumps, chlorination equipment, and distribution pumps
- Two reservoirs
- Two booster stations
Pumphouse #2 (Rundle Forebay surface water treatment plant):
- Surface water from Bow River supplies approximately half of the town.
- Capacity: 9 ML/day
- Level ll surface water treatment process includes coagulation, gravity filtration, chlorination and UV disinfection
- One reservoir
- One booster station
Process
Pumphouse #1:
Groundwater is chlorinated before being pumped to reservoirs, homes and businesses.
Pumphouse #2:
Water from Rundle Forebay is treated through a combination of chemical coagulation using alum, chlorine injection, gravity filtration and UV disinfection.