Aerial
Customer's Responsibilities
- Install all poles, anchors, and wire on the load side of the service connection point.
NOTE: The customer owns and maintains all poles, anchors, and wire on the load side of the service connection point.
EDTI's Responsibilities
- Install poles, anchors, and wire on the line side of the service connection point.
- Supply and install Current Transformers and Potential Transformers.
- Supply and install revenue metering equipment.
NOTE: EDTI owns and maintains all poles, anchors, Current Transformers, and Potential Transformers on the line side of the point of service.
Service Connection Point (Service Entry Point)
Second pole past the load side of the primary meter structure.
Point of Service Termination (Electrical Connection Point)
First pole past the load side of the primary meter structure (GI pole).