The DERP is fully responsible for:

  • All routine maintenance of the generator, control and protective equipment and recordkeeping for such maintenance.
  • Maintenance of the equipment on its side of the point of common coupling to accepted industry standards, in particular the Canadian Electrical Code (CEC) Part 1, Rule 2-300.

The DERP shall present to EDTI the planned maintenance procedures and a maintenance schedule for the interconnection protection equipment. Failure to maintain Canadian Electrical Code and other accepted industry standards for facilities and maintenance can result in the disconnection of the generator.

Maintenance on EDTI's distribution system will be carried out according to EDTI's distribution maintenance procedures and schedules.

Details on maintenance responsibilities will be outlined in the Interconnection Operating and Maintenance Agreement to be signed by both EDTI and the DERP.