In addition to the Valley Line West LRT Utility Relocation Project, an adjacent project, the City of Edmonton's 105 Avenue Streetscape Project, will begin in 2020 along 105 Avenue between 107 Street and 116 Street.
In advance of this project, we need to relocate utilities and construct a new storm tunnel, which will reduce odours, increase capacity of the system and reduce the risk of flooding.
In 2020, we'll be working between 107 Street and 114 Street with Power and Drainage work. A brief overview of the work is outlined below.