We'll be constructing 2 dry ponds, as well as performing sewer upgrades. This work is currently underway and is expected to be completed by the end of the 2020 construction season. Have a closer look at a more detailed project timeline.​

Project overview 

To reduce the risk of flooding during high-intensity, low-frequency rainfall events, we'll be constructing 2 dry ponds, as well as upgrading the sewer system in 2 locations in the area.

Dry pond timeline

The construction of the dry ponds has been completed. Fencing will remain around the dry ponds until approximately fall 2021 (one year upon completion of the landscaping). This is to allow the sod and other plantings time to properly root and grow.

Please note, these are still active worksites and are restricted areas. While we understand it is tempting to utilize these spaces, especially given the situation we are in with COVID-19, residents are asked not to remove the fencing or access the fenced area for their own safety and to prevent damage to the landscaping.

Any damage to the landscaping may impact the City of Edmonton's approval and significantly delay the opening of the space. Additional security measures will be put in place should residents enter the fenced worksites.

Find out how this work will impact you.

Sewer upgrade timeline

Alley 67 Avenue and west of 112 Street

The connection to the existing deep storm line on 67 Avenue has been completed and the road is now open.

An unexpected issue arose during construction relating to conflicts with the ATCO gas main in the alley which has delayed the completion of the work.

EPCOR and ATCO agreed to temporarily restore the alley to provide residents access over the winter. This work has been completed and the alley is now open. The City of Edmonton requested that pylons be placed along both sides of the alley to help delineate the roadway for the residents. The pylons will remain along the alley until spring.

As part of the temporary alley solution, EPCOR will implement a snow removal program as per City of Edmonton standards. Residents can expect the alley will be bladed to a smooth snow pack within five days from the end of snowfall. In addition, snow removal will be performed once 5cm of compacted snow has formed, or a heavy snowfall has occurred.

It is anticipated that ATCO will schedule the gas line relocation in 2021. ATCO will communicate directly with impacted residents when work is expected to begin and with further information on the work methodology.

Once the gas line relocation is complete, EPCOR will then complete the permanent restoration of the alley. Further details about the alley restoration will be communicated closer to the start of the work.

The City will be responsible for the maintenance of the alley once the project has been completed.

Along 62 Avenue and 112A Street

The sewer upgrade work along 62 Avenue and 112A Street has been completed. The road is now open to traffic.

The City of Edmonton has advised that planting of the replacement trees will occur in spring 2021.

Find out how this work will impact you.

Community garden

The start of construction for the replacement community garden is dependent on the approval of the proposed design. This process is still underway with EPCOR, the City of Edmonton and the Community Garden Committee. The garden is expected to start construction in spring 2021.