Timeline

The proposed re-zoning for the E.L. Smith Solar Farm project was approved in October 2020. The tentative schedule of work is as follows:

  • Construction of the solar farm is planned for early 2021.
  • Construction and installation of the battery is expected to begin in Summer 2021.
  • Completion of the solar farm and BESS project by Spring 2022.

Please note: These timelines are estimates and may change based on weather, procurement of materials, and construction conditions.

​Next steps​

The consultation process is ongoing and will continue throughout the duration of the project.