Navigate Up
Sign In

Have a Question? Ask Us!


​Project Update: Lansdowne Power System Upgrade

Last summer we began construction on our power system in the Lansdowne neighbourhood. We were able to complete the majority of our phase one work.

Phase Two Construction

We will be starting our phase two and remaining phase one work March 2013. We anticipate this work to take approximately five months, finishing in August 2013.

We Appreciate Your Patience

We would like to extend a thank you to the people of Lansdowne for their continued cooperation with the power system upgrade

Project Details

Last summer we began upgrading our power system in the Lansdowne area. This work will enable us to continue to provide you with safe and reliable power service. The work will be done in two phases and will involve replacing existing power equipment including:

  • Transformers
  • Cubicles
  • Power bases
  • Underground cables

Transformers

  • Most transformers will be replaced. Generally they will be in the same location and will be placed on concrete bases.
  • The new transformers will be similar in size (approximately 3’ x 3’ x 2’) and will be green in color.

Cubicles

  • Some existing cubicles will be replaced and installed in new locations.
  • The new cubicles will be similar in size (approximately 6’ x 5’ x 4’) and will be green in color.

Power bases

  • Some power bases, located at the bottom of streetlight poles, may need replacement and will be identified as we begin construction.

Replacing underground cables

  • This work will require trenching and directional drilling that will temporarily disturb some paved and landscaped areas in the neighbourhood.
  • Once construction is completed we will restore any areas impacted by the construction activity.

Timeline

Phase 1

Anticipated dates: July 2012 - November 2012
Location: South to south west portion of Lansdowne

Phase 2

Anticipated dates: Spring 2013 - Fall 2013
Location: North to north east portion of Lansdowne

What to expect during the project

Visual

What is directional drilling?
Directional drilling is a procesdure for installing pipe or cable underground without digging up the entire length of the route.

You can expect activity that is typical to construction, including a site trailer and company/contractor vehicles and equipment in the neighbourhood. Some typical construction activities that you may see include:

  • Digging holes behind all streetlight bases to pull out old cables.
  • Underground, directional drilling to place new cables.
  • Placement of concrete bases and installment of transformers.

Noise

Noise levels are not expected to exceed the allowable levels set by the City of Edmonton’s Community Standards Bylaw for Noise Control. Should it be necessary to temporarily exceed acceptable noise levels, we will apply to the City of Edmonton for a noise permit and will notify area residents of the proposed disruption.

Hours of Operation

We anticipate our hours of work to be Monday to Friday from 9:00 a.m. to 6:00 p.m. and occasional Saturdays.

Road Closures

No road closures are expected however there may be times where we need to temporarily block access to your driveway. Typically we would only block your driveway for approximately 1-2 hours and will provide you with as much notice as possible.

Power Supply

There will be some outages when we install the new transformers and cables are energized. We will try to minimize the outages while working on the project and will make every effort to provide you notice prior to any planned outage.

Work Space

We will require a two meter perimeter around existing transformers in order to install the new one.

Ground Disturbance

Landscaping and pavement will be removed as necessary for construction but will be kept to a minimum. We will restore any areas impacted by the construction activity.



 Click for a larger image

Contact Us

If you have questions or would like additional information please contact:

Michelle

Senior Advisor, Public Consultation
(780) 412-3234
publicconsultation@epcor.com

EPCOR Rain Barrel Sale